徐州鼓楼广场A地块工程
楼板裂缝处理方案
编制:
审核:
审批:
NO.2 CORP CHINA CONSTRUCTION THIRD ENGINEERING BUREAU
目 录
一、工程概况 ........................................................................................................................... 3
二、混凝土裂缝概述 ............................................................................................................... 3
三、板缝的处理意见 ............................................................................................................... 4
四、质量保证措施 ................................................................................................................... 4
五、保湿养护 ........................................................................................................................... 5
六、注意事项 ........................................................................................................................... 5
七、安全措施 ........................................................................................................................... 5
八、现场文明 ........................................................................................................................... 5
一、工程概况
本工程为徐州鼓楼广场综合发展项目A地块工程,包括1#~13#楼、桩基、地下车库及基坑支护工程。地上部分建筑面积约146750平方米、地下建筑面积约51062平方米、服务配套建筑面积约1100平方米。人防地下室为框架结构,1#~13#主楼为剪力墙结构。地下二层,1#、2#、3#、6#、7#、8#、9#塔楼地上34层,建筑总高度99.05米;4#、5#塔楼地上33层,建筑总高度96.15米;10#、11#、12#塔楼地上4层,建筑总高度13.4米;13#塔楼地上6层,建筑总高度19.600米。
二、混凝土裂缝概述
混凝土自从发明以来便在工程建设中被广泛使用。然而混凝土的裂缝较为普遍,在各种结构工程中裂缝几乎无所不在。尽管我们在施工中采取各种措施,但裂缝仍然时有出现。究其原因,我们对混凝土温度应力的变化的控制不到位是其产生裂缝的原因之一。具体分析裂缝产生的原因主要包含以下几方面:①荷载引起的裂缝、②温度变化引起的裂缝、③收缩引起的裂缝、④地基变形引起的裂缝、⑤钢筋锈蚀引起的裂缝、⑥冻胀引起的裂缝、⑦施工材料质量引起的裂缝、⑧施工工艺质量引起的裂缝。
当结构所处的环境正常,保护层厚度满足设计要求,无侵蚀介质,钢筋混凝土裂缝宽度可放宽至0.4mm;在湿气及土中为0.3mm;在海水及干湿交替中为0.15mm。沿钢筋的顺筋裂缝有害程度高,必须处理。裂缝深度h与结构厚度H的关系如下:h≤0.1H表面裂缝;0.1H<h<0.5H浅层裂缝;0.5H≤h<1.0H纵深裂缝;h=H贯穿裂缝。应当尽量避免贯穿性及纵深裂缝,如出现该种裂缝应采取化学灌浆处理来保证强度,即贯缝抗拉强度必须超过混凝土抗拉强度。
裂缝处理的方法主要包含以下:
(1)表面处理法
包括表面涂抹和表面贴补法,表面涂抹适用范围是浆材难以灌入的细而浅的裂缝,深度未达到钢筋表面的发丝裂缝,不漏水的裂缝,不伸缩的裂缝以及不在活动的裂缝。
(2)填充法
用修补材料直接填充裂缝,一般用来修补较宽的裂缝,作业简单,费用低。宽度小于0.3mm,深度较浅的裂缝、以及小规模裂缝的简易处理可采用取开V型槽,然后作填充处理。
三、板缝的处理意见
由于收缩裂缝属早期发展型,受环境影响继续发展的可能性不大。对裂缝观察2个多月后,板面裂缝不再发展,裂缝趋于稳定。并且不影响结构设计要求。我项目部采用有经验防水公司的施工方法并让其对楼板进行裂缝处理,具体施工工艺如下
1、施工工艺
(1)基面处理:沿裂缝处凿出宽度为10~15mm,深度为10㎜Ⅴ型槽,对混凝土表面出现的剥落、蜂窝等劣化现象的部位应予剔除,经检查无油脂、污迹后用空压机或吸尘器清理干净,基面必须要牢固、干净、平整充分润湿至饱和(但无积水,不平处先用水泥砂浆或水不漏找平),渗水严重的可在底部打引水孔。
(2)配料:施工时严格控制比例,将料按“堵漏灵”:水=1:0.25~0.35搅拌成腻子。
(3)上料:按“刮抹工法”的规定上料,若基面渗水严重,先在底部打引水孔降压,然后自上而下施工。上料时要稍用劲并来回多次使其密实,同时注意搭接。
(4)可用时间:在“堵漏灵”:水=1:0.25~0.35,环境温度20℃的条件下,速凝型“堵漏灵”的可用时间约3分钟。
(5)硬化时间:在“堵漏灵”:水=1:0.25~0.35,环境温度20℃的条件下,速凝型“堵漏灵”的硬化时间约5分钟(用50℃温水调料,可使硬化时间缩短至1~2分钟)。
2、漏水口施工工艺
(1)堵漏工法施工次序:堵漏→封口
(2)配料比例:“堵漏灵”:水=1:0.25~0.35。
(3)上料:根据口子形状将堵漏料捏成略小于口子尺寸的料团,放置一会儿(以手捏有硬感为宜)后塞进漏水口,并用木棒挤压,轻砸使其向四周挤实,即可瞬间止漏;然后在口子外面周围约10㎝处用抹子上一层刮抹料,堵漏前,口子周围可能要漏水的部位最好做防水处理,等涂层具有一定硬度后再堵漏,否则水可能从周围渗出。
四、质量保证措施
1、严格执行施工、技术交底,以及国家有关质量标准、施工及验收规范,保证不漏水、不渗水。
2、会同监理对作业队加强工序控制,加强施工管理,确保工程的施工质量。
3、不合格的施工,必须反工。
五、保湿养护
1、待涂层硬化后,马上进行保湿养护以防粉化,养护2~3天,第一次养护应小心以免破坏涂层。
2、养护方式可分为喷水、盖湿物、涂养护液等。
六、注意事项
1、夏季烈日下施工,需加强养护。
2、雨中施工,需防止雨水冲坏防水层。
七、安全措施
1.施工人员戴好安全帽,高空作业戴好安全带。
2.每一个作业小组由组长负责全面工作并兼管安全工作。
3.一切电气设备由专人管理及维修并安装保护器。
4.施工材料要放在安全地方,并不得有明火。
5.在高空作业时一切工具要稳当,以防坠物伤人。
6.遵守现场的安全文明施工管理制度。
7.用水用电符合甲方临水临电规范要求。
八、现场文明
1.工完场清,不得随意拆除安全防护设施。
2.尽量在白天施工,确需夜间作业时,应征求业主同意,做到不扰民。
3.抓好环保局工作,自觉控制噪声、粉尘。
徐州鼓楼广场A地块工程
楼板裂缝处理方案
编制:
审核:
审批:
NO.2 CORP CHINA CONSTRUCTION THIRD ENGINEERING BUREAU
目 录
一、工程概况 ........................................................................................................................... 3
二、混凝土裂缝概述 ............................................................................................................... 3
三、板缝的处理意见 ............................................................................................................... 4
四、质量保证措施 ................................................................................................................... 4
五、保湿养护 ........................................................................................................................... 5
六、注意事项 ........................................................................................................................... 5
七、安全措施 ........................................................................................................................... 5
八、现场文明 ........................................................................................................................... 5
一、工程概况
本工程为徐州鼓楼广场综合发展项目A地块工程,包括1#~13#楼、桩基、地下车库及基坑支护工程。地上部分建筑面积约146750平方米、地下建筑面积约51062平方米、服务配套建筑面积约1100平方米。人防地下室为框架结构,1#~13#主楼为剪力墙结构。地下二层,1#、2#、3#、6#、7#、8#、9#塔楼地上34层,建筑总高度99.05米;4#、5#塔楼地上33层,建筑总高度96.15米;10#、11#、12#塔楼地上4层,建筑总高度13.4米;13#塔楼地上6层,建筑总高度19.600米。
二、混凝土裂缝概述
混凝土自从发明以来便在工程建设中被广泛使用。然而混凝土的裂缝较为普遍,在各种结构工程中裂缝几乎无所不在。尽管我们在施工中采取各种措施,但裂缝仍然时有出现。究其原因,我们对混凝土温度应力的变化的控制不到位是其产生裂缝的原因之一。具体分析裂缝产生的原因主要包含以下几方面:①荷载引起的裂缝、②温度变化引起的裂缝、③收缩引起的裂缝、④地基变形引起的裂缝、⑤钢筋锈蚀引起的裂缝、⑥冻胀引起的裂缝、⑦施工材料质量引起的裂缝、⑧施工工艺质量引起的裂缝。
当结构所处的环境正常,保护层厚度满足设计要求,无侵蚀介质,钢筋混凝土裂缝宽度可放宽至0.4mm;在湿气及土中为0.3mm;在海水及干湿交替中为0.15mm。沿钢筋的顺筋裂缝有害程度高,必须处理。裂缝深度h与结构厚度H的关系如下:h≤0.1H表面裂缝;0.1H<h<0.5H浅层裂缝;0.5H≤h<1.0H纵深裂缝;h=H贯穿裂缝。应当尽量避免贯穿性及纵深裂缝,如出现该种裂缝应采取化学灌浆处理来保证强度,即贯缝抗拉强度必须超过混凝土抗拉强度。
裂缝处理的方法主要包含以下:
(1)表面处理法
包括表面涂抹和表面贴补法,表面涂抹适用范围是浆材难以灌入的细而浅的裂缝,深度未达到钢筋表面的发丝裂缝,不漏水的裂缝,不伸缩的裂缝以及不在活动的裂缝。
(2)填充法
用修补材料直接填充裂缝,一般用来修补较宽的裂缝,作业简单,费用低。宽度小于0.3mm,深度较浅的裂缝、以及小规模裂缝的简易处理可采用取开V型槽,然后作填充处理。
三、板缝的处理意见
由于收缩裂缝属早期发展型,受环境影响继续发展的可能性不大。对裂缝观察2个多月后,板面裂缝不再发展,裂缝趋于稳定。并且不影响结构设计要求。我项目部采用有经验防水公司的施工方法并让其对楼板进行裂缝处理,具体施工工艺如下
1、施工工艺
(1)基面处理:沿裂缝处凿出宽度为10~15mm,深度为10㎜Ⅴ型槽,对混凝土表面出现的剥落、蜂窝等劣化现象的部位应予剔除,经检查无油脂、污迹后用空压机或吸尘器清理干净,基面必须要牢固、干净、平整充分润湿至饱和(但无积水,不平处先用水泥砂浆或水不漏找平),渗水严重的可在底部打引水孔。
(2)配料:施工时严格控制比例,将料按“堵漏灵”:水=1:0.25~0.35搅拌成腻子。
(3)上料:按“刮抹工法”的规定上料,若基面渗水严重,先在底部打引水孔降压,然后自上而下施工。上料时要稍用劲并来回多次使其密实,同时注意搭接。
(4)可用时间:在“堵漏灵”:水=1:0.25~0.35,环境温度20℃的条件下,速凝型“堵漏灵”的可用时间约3分钟。
(5)硬化时间:在“堵漏灵”:水=1:0.25~0.35,环境温度20℃的条件下,速凝型“堵漏灵”的硬化时间约5分钟(用50℃温水调料,可使硬化时间缩短至1~2分钟)。
2、漏水口施工工艺
(1)堵漏工法施工次序:堵漏→封口
(2)配料比例:“堵漏灵”:水=1:0.25~0.35。
(3)上料:根据口子形状将堵漏料捏成略小于口子尺寸的料团,放置一会儿(以手捏有硬感为宜)后塞进漏水口,并用木棒挤压,轻砸使其向四周挤实,即可瞬间止漏;然后在口子外面周围约10㎝处用抹子上一层刮抹料,堵漏前,口子周围可能要漏水的部位最好做防水处理,等涂层具有一定硬度后再堵漏,否则水可能从周围渗出。
四、质量保证措施
1、严格执行施工、技术交底,以及国家有关质量标准、施工及验收规范,保证不漏水、不渗水。
2、会同监理对作业队加强工序控制,加强施工管理,确保工程的施工质量。
3、不合格的施工,必须反工。
五、保湿养护
1、待涂层硬化后,马上进行保湿养护以防粉化,养护2~3天,第一次养护应小心以免破坏涂层。
2、养护方式可分为喷水、盖湿物、涂养护液等。
六、注意事项
1、夏季烈日下施工,需加强养护。
2、雨中施工,需防止雨水冲坏防水层。
七、安全措施
1.施工人员戴好安全帽,高空作业戴好安全带。
2.每一个作业小组由组长负责全面工作并兼管安全工作。
3.一切电气设备由专人管理及维修并安装保护器。
4.施工材料要放在安全地方,并不得有明火。
5.在高空作业时一切工具要稳当,以防坠物伤人。
6.遵守现场的安全文明施工管理制度。
7.用水用电符合甲方临水临电规范要求。
八、现场文明
1.工完场清,不得随意拆除安全防护设施。
2.尽量在白天施工,确需夜间作业时,应征求业主同意,做到不扰民。
3.抓好环保局工作,自觉控制噪声、粉尘。